АлЭС / ЗТК

Plant profile · ЗТК

General information

Year Commissioned1963
Thermal Capacity1 100 Gcal/h
Fuel type
Annual fuel consumption
Coal reserve
Fuel-oil reserve
Personnel 173АУП 0ИТР 0ПП 0
Cost of supplied electricityCost of supplied heat
79%Heating-season readiness

Main equipment composition

Equipment composition is maintained in admin
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / ЗТК

Technical violation analysis · ЗТК

Operational control and comparative analysis
96%Operational stability
!Total violations42026
Open0
Closed3
ϟGrade I failure0
Total Downtime11,5 h

Workshop comparison

Workshop20252026ChangeGrade ITotal
Total000%00

Latest events

ПТВМ100-2 · —Внеплановый осмотр0,8 hClosed
ПТВМ100-1 · —Ограничение нагрузки6 hUnder Investigation
ПТВМ50-2 · —Замечание по вспомогательному оборудованию1,2 hClosed
ПТВМ50-1 · —Срабатывание технологической защиты3,5 hClosed
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / ЗТК

Repair schedule · ЗТК

8Repair completed
4Under repair
8Awaiting repair
CompletedПТВМ50-1
НС
ПТВМ100-3
ПТВМ100-4
Under repairПТВМ50-2
ПТВМ100-5
КВГМ100-4
ЮЗРК
Awaiting repairЦТРП-2
ПТВМ100-1
ПТВМ100-2
ПТВМ100-6
As of 08.09.2026Last edit 08.09.2026
Equipment / Repair Type
Apr
2026
May
2026
Jun
2026
Jul
2026
Aug
2026
Sep
2026
Oct
2026
Nov
2026
♨ ПТВМ50-1ТР
20.04–30.04
⚙ ЦТРП-2КР
28.04–23.05
♨ ПТВМ50-2СР
01.05–16.05
⚙ НСТР
09.05–08.06
♨ ПТВМ100-1ТР
12.05–01.06
♨ ПТВМ100-2КР
23.05–17.06
♨ ПТВМ100-3ТР
03.06–03.07
♨ ПТВМ100-4ТР
14.06–24.06
♨ ПТВМ100-5СР
25.06–10.07
♨ ПТВМ100-6ТР
06.07–26.07
♨ КВГМ100-1КР
17.07–11.08
♨ КВГМ100-2ТР
28.07–27.08
♨ КВГМ100-3ТР
08.08–18.08
♨ КВГМ100-4СР
19.08–03.09
♨ ДЕ-1ТР
30.08–19.09
♨ ДЕ-2КР
10.09–05.10
⚙ ЗРКТР
21.09–21.10
⚙ НЗКТР
02.10–12.10
Capital repairMedium repairCurrent repairDark segment — completed period
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / ЗТК

Heating Season Preparation Plan · ЗТК

Plan vs actual key production indicators
Overall preparation-plan execution
82,5%

Electricity generation

million kWh
Plan4 200Actual3 125Execution74.4%

Electricity supplied from busbars

million kWh
Plan3 950Actual2 876Execution72.8%

Heat supplied

thousand Gcal
Plan1 620Actual1 259Execution77.7%

Key preparation activities

Capital equipment repairs12 / 15 assets
80%
Fuel-facility preparation9 / 10 activities
90%
Personnel preparation8 / 8 activities
100%
Updated: 08.09.2026