АлЭС / ТЭЦ-1

Plant profile · ТЭЦ-1

General information

Year Commissioned1935 (1960)
ϟElectric Capacity145 MW
Thermal Capacity1 203 Gcal/h
Fuel type
Annual fuel consumption
Coal reserve
Fuel-oil reserve
Personnel 323АУП 0ИТР 0ПП 0
Cost of supplied electricityCost of supplied heat
62%Heating-season readiness

Main equipment composition

Equipment composition is maintained in admin
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / ТЭЦ-1

Technical violation analysis · ТЭЦ-1

Operational control and comparative analysis
96%Operational stability
!Total violations42026
Open0
Closed3
ϟGrade I failure0
Total Downtime11,5 h

Workshop comparison

Workshop20252026ChangeGrade ITotal
Total000%00

Latest events

КА-4 · —Внеплановый осмотр0,8 hClosed
КА-3 · —Ограничение нагрузки6 hUnder Investigation
КА-2 · —Замечание по вспомогательному оборудованию1,2 hClosed
КА-1 · —Срабатывание технологической защиты3,5 hClosed
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / ТЭЦ-1

Repair schedule · ТЭЦ-1

7Repair completed
3Under repair
6Awaiting repair
CompletedКА-1
КА-5
КА-6
ВК-4
Under repairКА-2
ВК-1
ВК-6
Awaiting repairКА-3
КА-4
ВК-2
ВК-3
As of 08.09.2026Last edit 08.09.2026
Equipment / Repair Type
Mar
2026
Apr
2026
May
2026
Jun
2026
Jul
2026
Aug
2026
Sep
2026
♨ КА-1ТР
15.03–25.03
♨ КА-2СР
26.03–10.04
♨ КА-3ТР
06.04–26.04
♨ КА-4КР
17.04–12.05
♨ КА-5ТР
28.04–28.05
♨ КА-6ТР
09.05–19.05
♨ ВК-1СР
20.05–04.06
♨ ВК-2ТР
31.05–20.06
♨ ВК-3КР
11.06–06.07
♨ ВК-4ТР
22.06–22.07
♨ ВК-5ТР
03.07–13.07
♨ ВК-6СР
14.07–29.07
♨ ВК-7ТР
25.07–14.08
✤ ТА-1КР
05.08–30.08
✤ ТА-2ТР
16.08–15.09
✤ ТА-3ТР
27.08–06.09
Capital repairMedium repairCurrent repairDark segment — completed period
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / ТЭЦ-1

Heating Season Preparation Plan · ТЭЦ-1

Plan vs actual key production indicators
Overall preparation-plan execution
82,5%

Electricity generation

million kWh
Plan4 200Actual3 125Execution74.4%

Electricity supplied from busbars

million kWh
Plan3 950Actual2 876Execution72.8%

Heat supplied

thousand Gcal
Plan1 620Actual1 259Execution77.7%

Key preparation activities

Capital equipment repairs12 / 15 assets
80%
Fuel-facility preparation9 / 10 activities
90%
Personnel preparation8 / 8 activities
100%
Updated: 08.09.2026