АлЭС / Капшагайская ГЭС

Plant profile · Капшагайская ГЭС

General information

Year Commissioned1970
ϟElectric Capacity364 MW
Fuel type
Annual fuel consumption
Coal reserve
Fuel-oil reserve
Personnel 135АУП 0ИТР 0ПП 0
Cost of supplied electricityCost of supplied heat
76%Heating-season readiness

Main equipment composition

Equipment composition is maintained in admin
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / Капшагайская ГЭС

Technical violation analysis · Капшагайская ГЭС

Operational control and comparative analysis
96%Operational stability
!Total violations42026
Open0
Closed3
ϟGrade I failure0
Total Downtime11,5 h

Workshop comparison

Workshop20252026ChangeGrade ITotal
Total000%00

Latest events

ГА-4 · —Внеплановый осмотр0,8 hClosed
ГА-3 · —Ограничение нагрузки6 hUnder Investigation
ГА-2 · —Замечание по вспомогательному оборудованию1,2 hClosed
ГА-1 · —Срабатывание технологической защиты3,5 hClosed
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / Капшагайская ГЭС

Repair schedule · Капшагайская ГЭС

1Repair completed
1Under repair
2Awaiting repair
CompletedГА-1
Under repairГА-2
Awaiting repairГА-3
ГА-4
As of 08.09.2026Last edit 08.09.2026
Equipment / Repair Type
Feb
2026
Mar
2026
Apr
2026
≋ ГА-1ТР
28.02–10.03
≋ ГА-2СР
11.03–26.03
≋ ГА-3ТР
22.03–11.04
≋ ГА-4КР
02.04–27.04
Capital repairMedium repairCurrent repairDark segment — completed period
Updated: 08.09.2026
АлЭС
ОЗП 2026–2027RELIABILITY · PEOPLE · SUSTAINABLE DEVELOPMENT
Offline viewAdmin
АлЭС / Капшагайская ГЭС

Heating Season Preparation Plan · Капшагайская ГЭС

Plan vs actual key production indicators
Overall preparation-plan execution
82,5%

Electricity generation

million kWh
Plan4 200Actual3 125Execution74.4%

Electricity supplied from busbars

million kWh
Plan3 950Actual2 876Execution72.8%

Heat supplied

thousand Gcal
Plan1 620Actual1 259Execution77.7%

Key preparation activities

Capital equipment repairs12 / 15 assets
80%
Fuel-facility preparation9 / 10 activities
90%
Personnel preparation8 / 8 activities
100%
Updated: 08.09.2026